Cyber Monday Deal : Flat 30% OFF! + free self-paced courses - SCHEDULE CALL
This exam is just to give you an idea of type of questions which may be asked in PMP Certification Exams. In examination you will get each question one by one on computer screen.
D. Reporting is easier
ANSWER – A
Explanation – Remember that if the question doesn’t state what it is comparing to, it is comparing to a functional organization.
ANSWER – A
Explanation – The project coordinator reports to a higher-level manager and has authority to make some decisions. The project expediter has no authority to make decisions.
ANSWER – A
Explanation – In a projectized organization, the entire company is organized by projects, giving the project manager the most power.
ANSWER – D
Choice D implies that the while project repeats every month. Generally, the only things that month repeat in a project are some activities. The while project does not repeat.
The critical element in a project's communication system is the:
Progress report
Project directive
Project manager
Customer
Answer- C
Explanation -A project manager facilitates all project-related communication
6. A project team member is talking to another team member and complaining that many people are asking him to do things. If he works in a functional organization, who has the power to give direction to the team members
A. The project manager
B. The functional manager
C. The team
D. Tight matrix
Answer- B
Explanation -In a functional organization, a functional manager is a team member’s boss and probably also the project manager’s boss.
7. A company is making an effort to improve its project performance and create historical records of past projects. What is the best way to accomplish this?
A. Create project management plans
B. Create lessons learnt
C. Create network diagrams
D. Create status reports
Answer- B
Explanation -Lessons learnt help to avoid future pitfalls and use the good ideas of past projects. This leads to improvements in future projects.
8. A market demand, a business need, and/ or a legal requirement are examples of?
Read: Top Short Term Courses to Invest in After Graduation
A. Reasons to hire project manager
B. Reasons projects are initiated
C. Reasons people or businesses becomes stakeholders
D. Reasons to sponsor a project
Answer- B
Explanation -These are all reasons projects are initiated.
8. A market demand, a business need, and/ or a legal requirement are examples of?
A. Reasons to hire project manager
B. Reasons projects are initiated
C. Reasons people or businesses becomes stakeholders
D. Reasons to sponsor a project
Answer- B
Explanation -These are all reasons projects are initiated.
9. Project scope is:
All the work that must be done in order to deliver a product according to the specified features and functions, only.
The features and functions that are to be included in a product or service.
A narrative description of work to be performed under contract.
Both A and B
Answer- A
Explanation -Project scope means all the work and only the work required to complete the project successfully
10. Your customer asks for a small change in the project, which was not budgeted in the project. It is a small effort as compared to the total project and you need the goodwill for a multimillion dollar on the pipeline. You will
A. Refuse to do the work
B. Agree to do the work at no charge
C. Do the work and bill him later
D. Assess the cost and schedule impact and tell them you will formalize the change request
Answer- D
Explanation -Impact of every change must be assessed and should go through change control
Answer- A
Explanation -In a functional organization, the project manager has the least support for the project and has little authority to assign resources. Choices C and D are roles in a weak matrix organization
12. A project manager has very little project experience, but he has been assigned as the project manager of a new project. Because he will be working in a matrix organization to complete his project, he can expect communications to be:
Answer- C
Explanation -Because a project done in a matrix organization involves people from across the organization, communications are more complex
Read: Why Choose JanBask Training For Oracle DBA Training
13. A manager and the head of engineering discuss a change to a major work package. After the meeting, the manager contacts you and tells you to complete the paperwork to make the change. This is an example of:
Management attention to scope management.
Management planning.
A project expediter position.
A change control system.
Answer- C
Explanation -This is an example of a project expediter position because you are not evaluating the change, looking for impacts, etc. You are merely implementing others request. In this case, you are acting as the project expediter
14. . The project is in the planning process group when three stakeholders come to the project manager asking for information on the company’s new' project management methodology. They want to know where it came from and why it is different from the way they currently manage projects. These stakeholders are also friends of the project manager, and the entire group has worked together for years. The project is using some new terms like “corrective action” that are making some stakeholders nervous, as they are unsure whether the way projects will be managed is going to change along with new terms. What should the project manager do?
Advise the stakeholders that she will keep them in the communication loop for the project.
Supply a list of new terms and their definitions.
Notify the project management office (PMO).
Make sure she maintains her authority as the project manager even though the stakeholders are her friends.
Answer- C
Explanation – Some students may think that this question has more than one right answer. It does not. There are many things the project manager can do, but should be done? The company policies are managed by the project management office and the project manager should make sure the stakeholders have clear information by sending them directly to the authority on company policies for project management.
15. Which of the following methods is least likely to be used for explaining project planning guidelines to the team?
Answer- D
Explanation- A report gives information about what happened and doesn't talk about planning or give guidelines or directives.
16. What is a program?
Answer – B
Explanation – Programs are group of related projects
17. Lessons learned are BEST completed by:
Answer – D
Explanation – Stakeholder, as their input is critical for collecting all the lessons learned on each project.
18. Operational work is different from project work, in that it is;
Answer – C
Explanation – Operational work is that which is ongoing to sustain an organization.
19. One of your team members informs you that he does not know which id the many projects he’s working on is the most important. Who should determine the priorities among the projects in a company?
Answer – C
Explanation – Because the questions talk about the priorities among projects which cannot be roll of other options given.
20. The project lifecycle differs from the product life cycle in that the project lifecycle;
Answer – B
Explanation – the project lifecycle is different for each industry, so choice B is the best answer
Read: Salesforce looks to the future with Einstein artificial intelligence
21. Management by objectives works only if;
Answer – A
Explanation – the best answer is the need for management to support the objective
22. Which of the following is a key output of the verify scope process?
Answer – B
Explanation – The output of the verify scope process is customer acceptance of project deliverables. Other options happen during project planning.
23. During what part of the project management process is the project scope statement created?
Answer – B
Explanation – The project scope is an output of the define scope process, which occurs during project planning.
24. The work breakdown structure can best be thought of as an effective aid for ________ communication.
Answer – D
Explanation – the term stakeholder encompasses all the other choices.
25. Verify scope is closely related to;
Answer – A
Explanation – Perform quality control, checks for correctness and verify scope checks for acceptance
26. The preparation of the scope baseline can best be described as involving
Answer – B
Explanation – After customer input, project team is responsible for scope baseline preparation.
27. Projects are initiated in response of:
Answer- D
Explanation- All those factors contribute towards project initiation.
28. The party that needs the change resulting from the project, and who will be its custodian on completion is the:
Answer- A
Answer- Project owner is the custodian
29. In which type of organization is team building likely to be most difficult?
Answer- C
Explanation- The team members report to multiple managers in matrix organizations.
30. A project kicks off meeting is usually conducted to:
Answer- A
Explanation- A kick-off meeting gets the project team onboard and announces the manager
Looking for PMP Online Training? Logon to JanBask Training , Global Leaders offering the best training classes
Read: Flourish In The Software Testing Industry By Getting Certified With Selenium Automated Tools
A dynamic, highly professional, and a global online training course provider committed to propelling the next generation of technology learners with a whole new way of training experience.
Cyber Security
QA
Salesforce
Business Analyst
MS SQL Server
Data Science
DevOps
Hadoop
Python
Artificial Intelligence
Machine Learning
Tableau
Search Posts
Related Posts
JanBask Training Gives a High Level of Business Analyst Training 268.8k
What is the Difference Between Business Analyst and Project Manager? 389k
The competition between Salesforce and Microsoft is intensifying continuously 785.9k
What is Polymorphism in Java? Type of Polymorphism in Java with Example 311.8k
Receive Latest Materials and Offers on Online IT Training Course
Interviews